BULGAH MINE

Bulgah gold ore transportation from the pit to process plant located around 65 kms from the pit .SCMS methodically blended the non heap leachable ore of different grades from the Bulgah open pit ore stockpile, and transported the ore to conducive ore processing circuit located around 65 kms from the ore blending site and fed to the crusher of the circuit. The total ore quantity handled was around 1,450,000 metric tons.

The blending and the transportation is accomplished utilizing SCMS’ own resources with full compliance to accuracy and safety as any variation in grade if that was deviated would have caused the deterimental effect on the gold recovery , thus the challenges of daily tonnages feed and the quality of the feed was successfully accomplished. This was at the Ma’aden operating gold mines at Bulgah and Sukhaybarat, which was first run indepentally by Boliden of Sweden taken over by Ma’aden to enhance the productivity from nearby deposits and satellite deposits.

  • Client

    Saudi Arabian Mining Company (Ma’aden)

  • Service Provided

    Mining and Transportation

HOW CAN WE HELP?

Got a question or need some help? Get in touch. We'd love to hear from you.